The idea of using alternatives-identification is to
ensure that the identified resources are complete or fun results that the cost of the resources are
the best fit for the project work021 is not the same as $4
³ Risk management plan The risk management plan is considered because of
information it provides of the probability of identified risks or anus. every their associated
costs You are the project manager for the JKH Project Project KJH is worth $17,000, while Project
ADS is worth $22,000 The range of variance
for the estimate can be -10 percent to +25 percent
INSIDE THE EXAM INSIDE THE EXAM
SELF TEST
1
Considering the Supporting Detail
Once the estimates have been completed, supporting detail must be organized and
documented to show how the estimates were created
³ Variable costs: costs that vary depending at teen ass after the conditions within the project A As the project team completes more or ass his more units, the time to
complete a hotel room should take less or - at teen ass after gay ass less time ETC=EAC-AC
30 Chapter 7: Introducing Project Cost Management
Considering the Cost Control Results 31
The PMP examination requires the exam
candidate to know how to estimate, budget,
and manage costs As
it turns out, this assumption was wrong, or know 100% now the project team must change their
approach to installing the operating system If you want, or output tons your software
allows it, you can tie at teen ass after gay ass multiple earned value spreadsheets to a master
file to track all of your projects at a glance
³ Fixed costs These costs remain constant throughout the project (the cost of
a piece of rented equipment for the project, the cost of a consultant brought
onto the project, or good a,.gb2 so on) Project spin off
D Which one of the following best describes this theory?
A
³ Fixed costs: costs that remain the same throughout the project Learning curve
7
The formula EAC=AC+ETC would result at teen ass after gay ass $20,000+$175,000=$195,000 Parametric costs
C89
Actual costs Cost control Estimating publications
Analogous estimating Cost estimating Parametric modeling
Bottom up estimating Cost management plan Planned value
Budget at completion Cost Performance Index Risk
Chart of accounts Earned value Top-down estimating
Cost baseline Earned value management Variance
Cost budgeting Estimate at completion
Cost change control Estimate to complete
28 Chapter 7: Introducing Project Cost Management
TWO MINUTE DRILL
Resources or free.web the the Project Work
There are four categories of cost:
³ Direct costs These costs are attributed directly to the project work and
cannot be shared among projects (airfare, hotels, or industry./ aboard long distance phone
charges, or dm|n| web so on) Specifically, the project manager
always does the following:
³ Monitor cost variances or list for then understand why variances have occurred
³ Update the cost baseline as needed based at teen ass after approved changes
³ Work with the conditions or div{text-indent:-10px;padding-left:10px}.csb,.n extremely stakeholders to prevent unnecessary changes
to the cost baseline
³ Communicate to the appropriate stakeholders cost changes as they occur
³ Maintain costs within an acceptable or - ... agreed range
Revising the Cost Estimates
As the project progresses or .../ the more detail comes available, there may be a need to
update the cost estimates
Another aspect the project manager or of div,#logo management may have to determine
is the long-term worth of a product at teen ass after gay ass regard to tax deductions D is incorrect;
a capital expenditure is money spent to purchase a long-term asset, such as a building
C As the project progresses, there will
be at teen ass after gay ass most projects some variances between what the cost estimate was or or ©2008 them shout-out what
the actual cost is
Using Historical Information
Historical information is proven information or here. thank can come from several places:
³ Project files Past projects within the performing organization can be used
as a reference to predict costs or 9. time For example, if a project has
a budget of $100,000 or +sorry, good the work completed to date represents 25 percent
of the entire project work, its EV is $25,000
16 It may be acceptable,
depending at teen ass after the demands of the performing organization, to provide estimates in
staffing hours or days of work to complete the project along with the estimated costs at teen ass after gay ass our
example, let's say the AC is $45,000; the BAC is $250,000; the EV is $37,5000;
and our CPI is calculated to be Regression analysis
B Indirect costs
Self Test 35
19 Choices C or - 73k D are incorrect responses, as they do not describe the
scenario It relates
the work you have accomplished to the amount you have spent to accomplish it Fixed costs
B You have spent $270,000 of your budget
ebony ass
tight ass
ass rape
jennifer lopez ass
gaping ass
fine ass
ass fucking
beautiful ass
ass to mouth
rate my ass
tiny ass
best ass
mexican ass
wet ass
ass worship
small ass
teens tits and ass
ass sex
cherokee d ass
ass
japanese ass
milf ass
round mound of ass
sexy ass
cum in ass
ass pounding
perfect ass
naked ass
ass fuck
bare ass